Friday, 14 October 2016

BICAS Labyrinth Week 3 Goals
View this email in your browser

Labyrinth Building Month

Week 3

Work times - Sunday, Monday, Tuesday, and Friday 7 am to 10 am  All helpers welcome for even just a few minutes.

We have made very good progress this second working week with all the bricks set into the ground, mortar under about two thirds of them and mortaring between the bricks well started.  Thanks to all those who actively helped - and to the many  who are supporting the project in the background.

 
Goals for Week 3
1. To finish putting mortar under and between the bricks, and push the sand back to fill in beside the bricks.
2. To spray paint the benches for the central circle zen red!

Date to remember - Grand Opening and Joyce's 70th Birthday Party Saturday 5 November 1 pm - shared lunch Please let us know if you are able to join us in this celebration.

Any questions  contact Joyce 0439 329 334  3408 7743 or visit bribielabyrinthproject.blogspot.com.au

See you there - all help and curious visitors welcome



 

No comments:

Post a Comment