Goals for the Week and Help Needed

1. Put up rope to define labyrinth area - and to keep cars from parking on labyrinth -  Painting hardwood sticks for supporting rope, and laying out rope.
2. Colouring 'No Parking Labyrinth Area' signs and hanging them on the rope.
3. Making a larger temporary sign to explain what is happening!
4. Laying out labyrinth in rope.
5. Picking up bricks from Ningi and Bellmere (probably on Saturday Oct 8) - a heavy duty trailer or utility would be helpful.

Date to remember - Grand Opening and Joyce's 70th Birthday Party Saturday 5 November 1 pm - shared lunch

Any questions  contact Joyce 0439 329 334  3408 7743

See you there - all help and curious visitors welcome